How long does a Single Construction Permit permit take in Bridgeland/Riverside, Calgary?
Median days · Applied → Issued
47 days
Sample: 13 permits, last 24 months
Median days · Issued → Completed
336 days
From permit issuance to completion
City-wide median
18 days
Bridgeland/Riverside is 29 days slower
Recent examples in Bridgeland/Riverside
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10026 | New | Willow and Stone Custom Homes | 2026-06-03 | 2026-08-17 | 75 | $426K |
| BP2026-07044 | New | Homes by Sorensen | 2026-04-28 | 2026-06-09 | 42 | $375K |
| BP2026-05423 | New | Platinum Homes Canada | 2026-04-07 | 2026-05-08 | 31 | $443K |
| BP2026-01959 | New | Your Property | 2026-02-09 | 2026-04-15 | 65 | $343K |
| BP2025-17518 | New | Sunset Homes | 2025-09-08 | 2025-12-08 | 91 | $488K |