How long does a Residential Improvement Project permit take in Bridgeland/Riverside, Calgary?

Rolling 24 months · Sample: 50
Median days · Applied → Issued
30 days
Sample: 50 permits, last 24 months
Median days · Issued → Completed
117 days
From permit issuance to completion
City-wide median
17 days
Bridgeland/Riverside is 13 days slower

Recent examples in Bridgeland/Riverside

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14194NewGeneration 3 Homes and Renovations2026-07-282026-08-2023$147K
BP2026-10027NewWillow and Stone Custom Homes2026-06-032026-08-1775$38K
BP2026-11803NewCaspian Contracting2026-06-252026-07-0611$47K
BP2026-10315Improvement2026-06-072026-06-2316$7K
BP2026-07064ImprovementDs Reno2026-04-282026-06-2255$2K