How long does a Demolition permit take in Bridgeland/Riverside, Calgary?
Median days · Applied → Issued
4 days
Sample: 25 permits, last 24 months
Median days · Issued → Completed
143 days
From permit issuance to completion
City-wide median
4 days
Same as Bridgeland/Riverside
Recent examples in Bridgeland/Riverside
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12007 | Demolition | Project Wize | 2026-06-29 | 2026-07-03 | 4 | $0 |
| BP2026-11397 | Demolition | Cloverhill Construction | 2026-06-21 | 2026-06-25 | 4 | $0 |
| BP2026-07029 | Demolition | Creative Solutions Contracting Services | 2026-04-28 | 2026-05-01 | 3 | $0 |
| BP2026-05165 | Demolition | Creative Solutions Contracting Services | 2026-04-02 | 2026-04-06 | 4 | $0 |
| BP2026-03323 | Demolition | Peterson Excavating | 2026-03-04 | 2026-03-23 | 19 | $0 |