How long does a Commercial / Multi Family Project permit take in Bridgeland/Riverside, Calgary?
Median days · Applied → Issued
43 days
Sample: 77 permits, last 24 months
Median days · Issued → Completed
101 days
From permit issuance to completion
City-wide median
42 days
Bridgeland/Riverside is 1 days slower
Recent examples in Bridgeland/Riverside
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-17291 | Unspecified | Omega Fire Protection | 2026-09-10 | 2026-09-11 | 1 | $3K |
| BP2026-03905 | New | Winter Green Homes | 2026-03-13 | 2026-09-08 | 179 | $631K |
| BP2026-05712 | New | Winter Green Homes | 2026-04-10 | 2026-09-02 | 145 | $818K |
| BP2026-12274 | Improvement | — | 2026-07-02 | 2026-08-27 | 56 | $20K |
| BP2026-12440 | Improvement | — | 2026-07-05 | 2026-08-20 | 46 | $0 |