How long does a Single Construction Permit permit take in Altadore, Calgary?

Rolling 24 months · Sample: 63
Median days · Applied → Issued
33 days
Sample: 63 permits, last 24 months
Median days · Issued → Completed
284 days
From permit issuance to completion
City-wide median
18 days
Altadore is 15 days slower

Recent examples in Altadore

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13741NewJerry Homes2026-07-222026-09-1151$536K
BP2026-11784NewHuber Homes2026-06-252026-08-1248$451K
BP2026-13008NewWillow Haven Designer Homes2026-07-132026-08-1230$340K
BP2026-14437NewLuxecraft Homes2026-07-302026-08-1112$437K
BP2026-11222NewJerry Homes2026-06-182026-07-2133$536K