How long does a Commercial / Multi Family Project permit take in Altadore, Calgary?
Median days · Applied → Issued
97 days
Sample: 42 permits, last 24 months
Median days · Issued → Completed
193 days
From permit issuance to completion
City-wide median
42 days
Altadore is 55 days slower
Recent examples in Altadore
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16282 | Unspecified | — | 2026-08-26 | 2026-08-28 | 2 | $6K |
| BP2026-05428 | New | William Blake Homes | 2026-04-07 | 2026-08-19 | 134 | $577K |
| BP2026-05446 | New | William Blake Homes | 2026-04-08 | 2026-08-19 | 133 | $585K |
| BP2026-10833 | Improvement | Joshua General Contracting | 2026-06-13 | 2026-08-19 | 67 | $25K |
| BP2026-08464 | Improvement | — | 2026-05-14 | 2026-08-17 | 95 | $30K |