How long does a Demolition permit take in Altadore, Calgary?
Median days · Applied → Issued
3 days
Sample: 60 permits, last 24 months
Median days · Issued → Completed
37 days
From permit issuance to completion
City-wide median
4 days
Altadore is 1 days faster
Recent examples in Altadore
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16268 | Demolition | Rocky View Excavation | 2026-08-26 | 2026-08-27 | 1 | $0 |
| BP2026-15347 | Demolition | Cloverhill Construction | 2026-08-13 | 2026-08-15 | 2 | $0 |
| BP2026-14599 | Demolition | Creative Solutions Contracting Services | 2026-08-04 | 2026-08-11 | 7 | $0 |
| BP2026-13306 | Demolition | Newgen Excavating | 2026-07-16 | 2026-07-17 | 1 | $0 |
| BP2026-12594 | Demolition | Western One Excavation | 2026-07-07 | 2026-07-09 | 2 | $0 |