How long does a Residential Improvement Project permit take in Altadore, Calgary?
Median days · Applied → Issued
28 days
Sample: 106 permits, last 24 months
Median days · Issued → Completed
148 days
From permit issuance to completion
City-wide median
17 days
Altadore is 11 days slower
Recent examples in Altadore
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11215 | Improvement | Concrete Cutting Geeks | 2026-06-18 | 2026-09-11 | 85 | $3K |
| BP2026-12190 | Improvement | Afcg Construction | 2026-06-30 | 2026-09-09 | 71 | $397K |
| BP2026-11963 | Improvement | — | 2026-06-28 | 2026-08-14 | 47 | $5K |
| BP2026-09698 | Improvement | — | 2026-05-31 | 2026-08-12 | 73 | $23K |
| BP2026-13009 | New | Willow Haven Designer Homes | 2026-07-13 | 2026-08-12 | 30 | $39K |