How long does a Single Construction Permit permit take in Windsor Park, Calgary?

Rolling 24 months · Sample: 22
Median days · Applied → Issued
30 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
499 days
From permit issuance to completion
City-wide median
18 days
Windsor Park is 12 days slower

Recent examples in Windsor Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14116NewLg Development and Construction2026-07-272026-08-2529$298K
BP2026-13602NewRenova Homes and Renovations2026-07-212026-08-2030$214K
BP2026-13604NewRenova Homes and Renovations2026-07-212026-08-2030$214K
BP2026-10610NewRoyal Design Homes2026-06-102026-07-2747$264K
BP2026-10612NewRoyal Design Homes2026-06-102026-07-2747$264K