How long does a Commercial / Multi Family Project permit take in Windsor Park, Calgary?
Median days · Applied → Issued
50 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
102 days
From permit issuance to completion
City-wide median
42 days
Windsor Park is 8 days slower
Recent examples in Windsor Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16932 | Unspecified | Banff Fire and Safety | 2026-09-03 | 2026-09-08 | 5 | $9K |
| BP2026-06668 | New | Gibb Construction | 2026-04-23 | 2026-08-28 | 127 | $763K |
| BP2026-06670 | New | Gibb Construction | 2026-04-23 | 2026-08-28 | 127 | $555K |
| BP2026-12282 | Improvement | — | 2026-07-02 | 2026-08-17 | 46 | $30K |
| BP2026-13866 | Improvement | Goat Restoration | 2026-07-23 | 2026-08-10 | 18 | $6K |