How long does a Commercial / Multi Family Project permit take in Windsor Park, Calgary?

Rolling 24 months · Sample: 43
Median days · Applied → Issued
50 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
102 days
From permit issuance to completion
City-wide median
42 days
Windsor Park is 8 days slower

Recent examples in Windsor Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16932UnspecifiedBanff Fire and Safety2026-09-032026-09-085$9K
BP2026-06668NewGibb Construction2026-04-232026-08-28127$763K
BP2026-06670NewGibb Construction2026-04-232026-08-28127$555K
BP2026-12282Improvement2026-07-022026-08-1746$30K
BP2026-13866ImprovementGoat Restoration2026-07-232026-08-1018$6K