How long does a Residential Improvement Project permit take in Windsor Park, Calgary?

Rolling 24 months · Sample: 36
Median days · Applied → Issued
28 days
Sample: 36 permits, last 24 months
Median days · Issued → Completed
201 days
From permit issuance to completion
City-wide median
17 days
Windsor Park is 11 days slower

Recent examples in Windsor Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14117NewLg Development and Construction2026-07-272026-08-2529$39K
BP2026-13603NewRenova Homes and Renovations2026-07-212026-08-2030$39K
BP2026-13605NewRenova Homes and Renovations2026-07-212026-08-2030$39K
BP2026-10611NewRoyal Design Homes2026-06-102026-07-2747$38K
BP2026-10613NewRoyal Design Homes2026-06-102026-07-2747$38K