How long does a Residential Improvement Project permit take in Wildwood, Calgary?
Median days · Applied → Issued
30 days
Sample: 41 permits, last 24 months
Median days · Issued → Completed
155 days
From permit issuance to completion
City-wide median
17 days
Wildwood is 13 days slower
Recent examples in Wildwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13585 | New | Wildwood Developments | 2026-07-21 | 2026-09-09 | 50 | $37K |
| BP2026-10862 | Improvement | — | 2026-06-14 | 2026-09-01 | 79 | $91K |
| BP2026-14674 | Improvement | — | 2026-08-04 | 2026-08-26 | 22 | $40K |
| BP2026-11383 | New | — | 2026-06-20 | 2026-07-13 | 23 | $106K |
| BP2026-10534 | Improvement | Smith Property Services Smith Property Renovations | 2026-06-10 | 2026-06-24 | 14 | $75K |