How long does a Demolition permit take in Wildwood, Calgary?
Median days · Applied → Issued
4 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
58 days
From permit issuance to completion
City-wide median
4 days
Same as Wildwood
Recent examples in Wildwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16609 | Demolition | Newgen Excavating | 2026-08-31 | 2026-09-08 | 8 | $0 |
| BP2026-15095 | Demolition | Ledgestone Signature Homes | 2026-08-10 | 2026-08-12 | 2 | $0 |
| BP2026-14710 | Demolition | Luminous Star Abatement | 2026-08-05 | 2026-08-06 | 1 | $0 |
| BP2026-11541 | Demolition | Newgen Excavating | 2026-06-23 | 2026-06-24 | 1 | $0 |
| BP2026-11067 | Demolition | Dynamic Dirt Works | 2026-06-16 | 2026-06-17 | 1 | $0 |