How long does a Commercial / Multi Family Project permit take in Wildwood, Calgary?
Median days · Applied → Issued
70 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
147 days
From permit issuance to completion
City-wide median
42 days
Wildwood is 28 days slower
Recent examples in Wildwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05831 | New | Winter Green Homes | 2026-04-13 | 2026-09-09 | 149 | $934K |
| BP2026-06064 | New | National Star Homes | 2026-04-16 | 2026-07-15 | 90 | $542K |
| BP2025-19433 | New | Archway Developments | 2025-10-03 | 2025-12-12 | 70 | $774K |
| BP2025-16922 | Improvement | — | 2025-08-29 | 2025-10-22 | 54 | $80K |
| BP2025-07362 | Improvement | — | 2025-04-24 | 2025-05-26 | 32 | $200K |