How long does a Commercial / Multi Family Project permit take in Wildwood, Calgary?

Rolling 24 months · Sample: 7
Median days · Applied → Issued
70 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
147 days
From permit issuance to completion
City-wide median
42 days
Wildwood is 28 days slower

Recent examples in Wildwood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-05831NewWinter Green Homes2026-04-132026-09-09149$934K
BP2026-06064NewNational Star Homes2026-04-162026-07-1590$542K
BP2025-19433NewArchway Developments2025-10-032025-12-1270$774K
BP2025-16922Improvement2025-08-292025-10-2254$80K
BP2025-07362Improvement2025-04-242025-05-2632$200K