How long does a Single Construction Permit permit take in West Hillhurst, Calgary?

Rolling 24 months · Sample: 68
Median days · Applied → Issued
41 days
Sample: 68 permits, last 24 months
Median days · Issued → Completed
312 days
From permit issuance to completion
City-wide median
18 days
West Hillhurst is 23 days slower

Recent examples in West Hillhurst

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-01000New1824457 Alberta2026-01-212026-07-30190$348K
BP2026-06927NewNew Realm Homes2026-04-272026-07-1579$345K
BP2026-06929NewNew Realm Homes2026-04-272026-07-1579$345K
BP2026-09207NewVesta Properties2026-05-262026-07-0742$0
BP2026-09208NewVesta Properties2026-05-262026-07-0742$0