How long does a Commercial / Multi Family Project permit take in West Hillhurst, Calgary?
Median days · Applied → Issued
82 days
Sample: 53 permits, last 24 months
Median days · Issued → Completed
224 days
From permit issuance to completion
City-wide median
42 days
West Hillhurst is 40 days slower
Recent examples in West Hillhurst
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13855 | Improvement | — | 2026-07-23 | 2026-09-09 | 48 | $10K |
| BP2026-14542 | New | Mp Homes | 2026-08-03 | 2026-08-28 | 25 | $678K |
| BP2025-23598 | New | Arveco | 2025-12-11 | 2026-08-12 | 244 | $1.4M |
| BP2026-06974 | New | — | 2026-04-28 | 2026-08-04 | 98 | $800K |
| BP2026-02955 | New | Kalamoir Construction | 2026-02-26 | 2026-07-06 | 130 | $764K |