How long does a Demolition permit take in West Hillhurst, Calgary?
Median days · Applied → Issued
4 days
Sample: 58 permits, last 24 months
Median days · Issued → Completed
35 days
From permit issuance to completion
City-wide median
4 days
Same as West Hillhurst
Recent examples in West Hillhurst
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15815 | Demolition | Srp Projects | 2026-08-19 | 2026-08-21 | 2 | $0 |
| BP2026-14786 | Demolition | Ark Construction | 2026-08-06 | 2026-08-11 | 5 | $0 |
| BP2026-14692 | Demolition | Cloverhill Construction | 2026-08-05 | 2026-08-06 | 1 | $0 |
| BP2026-13726 | Demolition | P and G Excavating Trucking | 2026-07-22 | 2026-07-27 | 5 | $0 |
| BP2026-07079 | Demolition | Cloverhill Construction | 2026-04-28 | 2026-07-09 | 72 | $0 |