How long does a Single Construction Permit permit take in Varsity, Calgary?
Median days · Applied → Issued
33 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
309 days
From permit issuance to completion
City-wide median
18 days
Varsity is 15 days slower
Recent examples in Varsity
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13926 | New | Stanley Signature Homes | 2026-07-24 | 2026-09-08 | 46 | $248K |
| BP2026-13928 | New | Stanley Signature Homes | 2026-07-24 | 2026-09-08 | 46 | $248K |
| BP2026-04373 | New | Platinum Build Homes | 2026-03-21 | 2026-04-24 | 34 | $549K |
| BP2025-20895 | New | Grandscape Homes | 2025-10-26 | 2025-11-06 | 11 | $467K |
| BP2025-19675 | New | Van Manna Homes | 2025-10-07 | 2025-10-27 | 20 | $594K |