How long does a Demolition permit take in Varsity, Calgary?

Rolling 24 months · Sample: 24
Median days · Applied → Issued
3 days
Sample: 24 permits, last 24 months
Median days · Issued → Completed
102 days
From permit issuance to completion
City-wide median
4 days
Varsity is 1 days faster

Recent examples in Varsity

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15041DemolitionDelta Excavating and Trucking2026-08-102026-08-155$0
BP2026-13639DemolitionCloverhill Construction2026-07-212026-07-243$0
BP2026-11153DemolitionLuminous Star Abatement2026-06-172026-06-247$0
BP2026-11129DemolitionDelta Excavating and Trucking2026-06-172026-06-181$0
BP2026-00276DemolitionWestern One Excavation2026-01-082026-04-1395$0