How long does a Commercial / Multi Family Project permit take in Varsity, Calgary?
Median days · Applied → Issued
39 days
Sample: 87 permits, last 24 months
Median days · Issued → Completed
103 days
From permit issuance to completion
City-wide median
42 days
Varsity is 3 days faster
Recent examples in Varsity
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10944 | Improvement | Buttcon West | 2026-06-15 | 2026-09-05 | 82 | $6M |
| BP2026-15360 | Improvement | — | 2026-08-13 | 2026-09-03 | 21 | $401K |
| BP2026-14571 | Improvement | — | 2026-08-04 | 2026-08-18 | 14 | $3K |
| BP2026-02387 | Improvement | Copperstone Homes | 2026-02-17 | 2026-08-13 | 177 | $250K |
| BP2026-11882 | Improvement | Westcor Construction | 2026-06-26 | 2026-08-11 | 46 | $95K |