How long does a Residential Improvement Project permit take in Tuxedo Park, Calgary?

Rolling 24 months · Sample: 60
Median days · Applied → Issued
20 days
Sample: 60 permits, last 24 months
Median days · Issued → Completed
92 days
From permit issuance to completion
City-wide median
17 days
Tuxedo Park is 3 days slower

Recent examples in Tuxedo Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15093Improvement2026-08-102026-08-2616$36K
BP2026-11196ImprovementAsencio Built Construction2026-06-182026-07-2032$32K
BP2026-06709ImprovementFarmboy Contracting2026-04-232026-07-1684$12K
BP2026-11493Improvement2026-06-222026-07-0210$16K
BP2026-06499NewBee Renovations2026-04-222026-06-0847$38K