How long does a Commercial / Multi Family Project permit take in Tuxedo Park, Calgary?
Median days · Applied → Issued
79 days
Sample: 54 permits, last 24 months
Median days · Issued → Completed
184 days
From permit issuance to completion
City-wide median
42 days
Tuxedo Park is 37 days slower
Recent examples in Tuxedo Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-22712 | Improvement | — | 2025-11-26 | 2026-09-02 | 280 | $175K |
| BP2026-04776 | New | Sunset Homes | 2026-03-26 | 2026-08-22 | 149 | $1.4M |
| BP2026-06019 | New | Siena Signature Builders | 2026-04-15 | 2026-08-11 | 118 | $628K |
| BP2026-04087 | New | — | 2026-03-17 | 2026-07-28 | 133 | $18.2M |
| BP2026-08323 | New | Abstract Developments | 2026-05-13 | 2026-07-17 | 65 | $321K |