How long does a Demolition permit take in Tuxedo Park, Calgary?
Median days · Applied → Issued
4 days
Sample: 51 permits, last 24 months
Median days · Issued → Completed
81 days
From permit issuance to completion
City-wide median
4 days
Same as Tuxedo Park
Recent examples in Tuxedo Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16217 | Demolition | Splendor Excavation | 2026-08-25 | 2026-08-27 | 2 | $0 |
| BP2026-15211 | Demolition | Foundex Ground Services | 2026-08-11 | 2026-08-15 | 4 | $0 |
| BP2026-14685 | Demolition | Apex Excavating and Trucking | 2026-08-05 | 2026-08-11 | 6 | $0 |
| BP2026-13576 | Demolition | Western One Excavation | 2026-07-21 | 2026-07-24 | 3 | $0 |
| BP2026-12840 | Demolition | Cloverhill Construction | 2026-07-10 | 2026-07-13 | 3 | $0 |