How long does a Residential Improvement Project permit take in Sunnyside, Calgary?
Median days · Applied → Issued
32 days
Sample: 13 permits, last 24 months
Median days · Issued → Completed
113 days
From permit issuance to completion
City-wide median
17 days
Sunnyside is 15 days slower
Recent examples in Sunnyside
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11057 | New | Toy Box Garage | 2026-06-16 | 2026-09-11 | 87 | $51K |
| BP2026-02888 | New | Brookwright | 2026-02-25 | 2026-05-12 | 76 | $54K |
| BP2026-06495 | New | Bravehomes | 2026-04-21 | 2026-05-11 | 20 | $46K |
| BP2026-01411 | Improvement | — | 2026-01-30 | 2026-04-10 | 70 | $150K |
| BP2026-03806 | Improvement | True North Concrete Cutting and Coring | 2026-03-12 | 2026-03-23 | 11 | $4K |