How long does a Commercial / Multi Family Project permit take in Sunnyside, Calgary?
Median days · Applied → Issued
122 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
82 days
From permit issuance to completion
City-wide median
42 days
Sunnyside is 80 days slower
Recent examples in Sunnyside
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-00522 | New | Murari Homes | 2026-01-13 | 2026-08-10 | 209 | $918K |
| BP2026-10657 | Improvement | — | 2026-06-11 | 2026-07-27 | 46 | $3K |
| BP2026-03134 | New | Atco Structures and Logistics | 2026-03-02 | 2026-07-10 | 130 | $14.9M |
| BP2025-20958 | New | Q | 2025-10-27 | 2026-06-08 | 224 | $1.3M |
| BP2026-06796 | New | Baadani Development | 2026-04-24 | 2026-05-19 | 25 | $31K |