How long does a Demolition permit take in Sunnyside, Calgary?
Median days · Applied → Issued
3 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
37 days
From permit issuance to completion
City-wide median
4 days
Sunnyside is 1 days faster
Recent examples in Sunnyside
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-17228 | Demolition | Foundex Ground Services | 2026-09-09 | 2026-09-09 | 0 | $0 |
| BP2026-10931 | Demolition | Ground Shakers Excavating | 2026-06-15 | 2026-06-23 | 8 | $0 |
| BP2026-05847 | Demolition | Ovis Group | 2026-04-13 | 2026-04-14 | 1 | $0 |
| BP2025-19193 | Demolition | Cloverhill Construction | 2025-09-30 | 2025-10-03 | 3 | $0 |
| BP2025-19194 | Demolition | Cloverhill Construction | 2025-09-30 | 2025-10-01 | 1 | $0 |