How long does a Demolition permit take in Sunnyside, Calgary?

Rolling 24 months · Sample: 7
Median days · Applied → Issued
3 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
37 days
From permit issuance to completion
City-wide median
4 days
Sunnyside is 1 days faster

Recent examples in Sunnyside

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-17228DemolitionFoundex Ground Services2026-09-092026-09-090$0
BP2026-10931DemolitionGround Shakers Excavating2026-06-152026-06-238$0
BP2026-05847DemolitionOvis Group2026-04-132026-04-141$0
BP2025-19193DemolitionCloverhill Construction2025-09-302025-10-033$0
BP2025-19194DemolitionCloverhill Construction2025-09-302025-10-011$0