How long does a Residential Improvement Project permit take in Sunalta, Calgary?
Median days · Applied → Issued
37 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
28 days
From permit issuance to completion
City-wide median
17 days
Sunalta is 20 days slower
Recent examples in Sunalta
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-02756 | Improvement | — | 2026-02-24 | 2026-08-25 | 182 | $300K |
| BP2026-03129 | Improvement | — | 2026-03-02 | 2026-04-21 | 50 | $5K |
| BP2025-20872 | Improvement | — | 2025-10-24 | 2025-11-06 | 13 | $0 |
| BP2025-19162 | New | — | 2025-09-29 | 2025-10-23 | 24 | $72K |
| BP2024-15541 | Improvement | — | 2024-07-29 | 2024-12-05 | 129 | $5K |