How long does a Residential Improvement Project permit take in Sunalta, Calgary?

Rolling 24 months · Sample: 6
Median days · Applied → Issued
37 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
28 days
From permit issuance to completion
City-wide median
17 days
Sunalta is 20 days slower

Recent examples in Sunalta

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-02756Improvement2026-02-242026-08-25182$300K
BP2026-03129Improvement2026-03-022026-04-2150$5K
BP2025-20872Improvement2025-10-242025-11-0613$0
BP2025-19162New2025-09-292025-10-2324$72K
BP2024-15541Improvement2024-07-292024-12-05129$5K