How long does a Demolition permit take in Sunalta, Calgary?
Median days · Applied → Issued
5 days
Sample: 19 permits, last 24 months
Median days · Issued → Completed
157 days
From permit issuance to completion
City-wide median
4 days
Sunalta is 1 days slower
Recent examples in Sunalta
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-23069 | Demolition | Sbi Strategic | 2025-12-02 | 2025-12-05 | 3 | $0 |
| BP2025-23071 | Demolition | Sbi Strategic | 2025-12-02 | 2025-12-05 | 3 | $0 |
| BP2025-16352 | Demolition | Ovis Group | 2025-08-21 | 2025-08-27 | 6 | $0 |
| BP2025-16354 | Demolition | Ovis Group | 2025-08-21 | 2025-08-27 | 6 | $0 |
| BP2025-16351 | Demolition | Ovis Group | 2025-08-21 | 2025-08-26 | 5 | $0 |