How long does a Commercial / Multi Family Project permit take in Sunalta, Calgary?
Median days · Applied → Issued
69 days
Sample: 27 permits, last 24 months
Median days · Issued → Completed
106 days
From permit issuance to completion
City-wide median
42 days
Sunalta is 27 days slower
Recent examples in Sunalta
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13954 | Unspecified | — | 2026-07-24 | 2026-08-31 | 38 | $2K |
| BP2026-10780 | Improvement | — | 2026-06-12 | 2026-07-24 | 42 | $250K |
| BP2026-11675 | Improvement | Goldmark Homes | 2026-06-24 | 2026-07-21 | 27 | $42K |
| BP2026-10615 | Unspecified | Site Connect | 2026-06-10 | 2026-06-16 | 6 | $85K |
| BP2025-12858 | New | Lear | 2025-07-03 | 2026-06-04 | 336 | $37.9M |