How long does a Single Construction Permit permit take in St. Andrews Heights, Calgary?

Rolling 24 months · Sample: 11
Median days · Applied → Issued
34 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
348 days
From permit issuance to completion
City-wide median
18 days
St. Andrews Heights is 16 days slower

Recent examples in St. Andrews Heights

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11677NewElite Craft Builders2026-06-242026-08-1249$596K
BP2026-10867NewCedar Rock Homes2026-06-152026-07-2944$622K
BP2025-23639NewFour Corners Contracting2025-12-122026-01-0827$712K
BP2025-15079NewRiverside Developments2025-08-042025-09-0835$665K
BP2025-10816NewCalton Developments2025-06-062025-06-1812$0