How long does a Commercial / Multi Family Project permit take in St. Andrews Heights, Calgary?
Median days · Applied → Issued
29 days
Sample: 33 permits, last 24 months
Median days · Issued → Completed
92 days
From permit issuance to completion
City-wide median
42 days
St. Andrews Heights is 13 days faster
Recent examples in St. Andrews Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12281 | Improvement | Synergy Projects | 2026-07-02 | 2026-09-04 | 64 | $10.5M |
| BP2026-14866 | Improvement | PCL Construction | 2026-08-06 | 2026-09-04 | 29 | $294K |
| BP2026-04711 | Improvement | PCL Construction | 2026-03-26 | 2026-08-07 | 134 | $2.8M |
| BP2026-09506 | Improvement | — | 2026-05-29 | 2026-07-14 | 46 | $5.3M |
| BP2026-11534 | Improvement | EllisDon Construction | 2026-06-23 | 2026-06-29 | 6 | $566K |