How long does a Demolition permit take in St. Andrews Heights, Calgary?
Median days · Applied → Issued
3 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
88 days
From permit issuance to completion
City-wide median
4 days
St. Andrews Heights is 1 days faster
Recent examples in St. Andrews Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15789 | Demolition | Cloverhill Construction | 2026-08-19 | 2026-08-26 | 7 | $0 |
| BP2026-15852 | Demolition | Srp Projects | 2026-08-20 | 2026-08-21 | 1 | $0 |
| BP2026-10742 | Demolition | Creative Solutions Contracting Services | 2026-06-12 | 2026-06-24 | 12 | $0 |
| BP2026-10047 | Demolition | Apex Excavating and Trucking | 2026-06-03 | 2026-06-11 | 8 | $0 |
| BP2026-04641 | Demolition | Ovis Group | 2026-03-25 | 2026-04-02 | 8 | $0 |