How long does a Single Construction Permit permit take in Spruce Cliff, Calgary?

Rolling 24 months · Sample: 11
Median days · Applied → Issued
27 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
350 days
From permit issuance to completion
City-wide median
18 days
Spruce Cliff is 9 days slower

Recent examples in Spruce Cliff

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12393NewPeer Homes and Developments2026-07-032026-08-2856$433K
BP2025-18653NewParamount Homes2025-09-232025-10-2229$226K
BP2025-18655NewParamount Homes2025-09-232025-10-2229$226K
BP2025-09051NewEasy Homes2025-05-142025-05-2814$327K
BP2025-08455NewEasy Homes2025-05-072025-05-2720$327K