How long does a Commercial / Multi Family Project permit take in Spruce Cliff, Calgary?
Median days · Applied → Issued
45 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
212 days
From permit issuance to completion
City-wide median
42 days
Spruce Cliff is 3 days slower
Recent examples in Spruce Cliff
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07154 | New | Kalamoir Construction | 2026-04-29 | 2026-09-03 | 127 | $485K |
| BP2026-07151 | New | Kalamoir Construction | 2026-04-29 | 2026-08-21 | 114 | $483K |
| BP2026-07150 | New | Kalamoir Construction | 2026-04-29 | 2026-08-13 | 106 | $479K |
| BP2026-06478 | New | Arveco | 2026-04-21 | 2026-06-05 | 45 | $501K |
| BP2026-06480 | New | Arveco | 2026-04-21 | 2026-06-05 | 45 | $765K |