How long does a Commercial / Multi Family Project permit take in Spruce Cliff, Calgary?

Rolling 24 months · Sample: 15
Median days · Applied → Issued
45 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
212 days
From permit issuance to completion
City-wide median
42 days
Spruce Cliff is 3 days slower

Recent examples in Spruce Cliff

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07154NewKalamoir Construction2026-04-292026-09-03127$485K
BP2026-07151NewKalamoir Construction2026-04-292026-08-21114$483K
BP2026-07150NewKalamoir Construction2026-04-292026-08-13106$479K
BP2026-06478NewArveco2026-04-212026-06-0545$501K
BP2026-06480NewArveco2026-04-212026-06-0545$765K