How long does a Residential Improvement Project permit take in Spruce Cliff, Calgary?

Rolling 24 months · Sample: 28
Median days · Applied → Issued
22 days
Sample: 28 permits, last 24 months
Median days · Issued → Completed
295 days
From permit issuance to completion
City-wide median
17 days
Spruce Cliff is 5 days slower

Recent examples in Spruce Cliff

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-04495New2026-03-242026-09-02162$65K
BP2026-12394NewPeer Homes and Developments2026-07-032026-08-2856$39K
BP2026-15353ImprovementPaul Davis Red Deer2026-08-132026-08-2714$25K
BP2026-02246ImprovementPolar Peak Construction2026-02-132026-04-2975$71K
BP2025-23438ImprovementYour Custom Home Your General Contractor2025-12-092026-01-0729$45K