How long does a Single Construction Permit permit take in South Calgary, Calgary?

Rolling 24 months · Sample: 20
Median days · Applied → Issued
28 days
Sample: 20 permits, last 24 months
Median days · Issued → Completed
276 days
From permit issuance to completion
City-wide median
18 days
South Calgary is 10 days slower

Recent examples in South Calgary

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-02446NewHbc Custom Homes2026-02-182026-03-0414$356K
BP2026-02448NewHbc Custom Homes2026-02-182026-03-0414$356K
BP2025-22327New2025-11-192026-02-1083$0
BP2026-00083NewCnj Developments2026-01-052026-01-2823$407K
BP2025-20679NewCnj Developments2025-10-222025-11-2635$387K