How long does a Single Construction Permit permit take in South Calgary, Calgary?
Median days · Applied → Issued
28 days
Sample: 20 permits, last 24 months
Median days · Issued → Completed
276 days
From permit issuance to completion
City-wide median
18 days
South Calgary is 10 days slower
Recent examples in South Calgary
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-02446 | New | Hbc Custom Homes | 2026-02-18 | 2026-03-04 | 14 | $356K |
| BP2026-02448 | New | Hbc Custom Homes | 2026-02-18 | 2026-03-04 | 14 | $356K |
| BP2025-22327 | New | — | 2025-11-19 | 2026-02-10 | 83 | $0 |
| BP2026-00083 | New | Cnj Developments | 2026-01-05 | 2026-01-28 | 23 | $407K |
| BP2025-20679 | New | Cnj Developments | 2025-10-22 | 2025-11-26 | 35 | $387K |