How long does a Commercial / Multi Family Project permit take in South Calgary, Calgary?
Median days · Applied → Issued
61 days
Sample: 80 permits, last 24 months
Median days · Issued → Completed
98 days
From permit issuance to completion
City-wide median
42 days
South Calgary is 19 days slower
Recent examples in South Calgary
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16267 | Unspecified | Sprouse Fire and Safety | 2026-08-26 | 2026-08-27 | 1 | $5K |
| BP2026-08723 | Improvement | — | 2026-05-19 | 2026-08-19 | 92 | $0 |
| BP2026-07043 | Improvement | — | 2026-04-28 | 2026-07-23 | 86 | $0 |
| BP2026-10434 | Improvement | Tayo Construction | 2026-06-09 | 2026-07-06 | 27 | $250K |
| BP2026-11088 | Unspecified | — | 2026-06-17 | 2026-06-30 | 13 | $2K |