How long does a Commercial / Multi Family Project permit take in South Calgary, Calgary?

Rolling 24 months · Sample: 80
Median days · Applied → Issued
61 days
Sample: 80 permits, last 24 months
Median days · Issued → Completed
98 days
From permit issuance to completion
City-wide median
42 days
South Calgary is 19 days slower

Recent examples in South Calgary

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16267UnspecifiedSprouse Fire and Safety2026-08-262026-08-271$5K
BP2026-08723Improvement2026-05-192026-08-1992$0
BP2026-07043Improvement2026-04-282026-07-2386$0
BP2026-10434ImprovementTayo Construction2026-06-092026-07-0627$250K
BP2026-11088Unspecified2026-06-172026-06-3013$2K