How long does a Residential Improvement Project permit take in South Calgary, Calgary?
Median days · Applied → Issued
22 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
96 days
From permit issuance to completion
City-wide median
17 days
South Calgary is 5 days slower
Recent examples in South Calgary
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13209 | Improvement | — | 2026-07-15 | 2026-08-07 | 23 | $15 |
| BP2026-11400 | Improvement | — | 2026-06-21 | 2026-07-07 | 16 | $5K |
| BP2026-04208 | Improvement | West Era Homes | 2026-03-19 | 2026-06-19 | 92 | $79K |
| BP2026-02090 | Improvement | — | 2026-02-11 | 2026-04-02 | 50 | $30K |
| BP2026-03663 | Improvement | — | 2026-03-10 | 2026-03-19 | 9 | $0 |