How long does a Residential Improvement Project permit take in South Calgary, Calgary?

Rolling 24 months · Sample: 35
Median days · Applied → Issued
22 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
96 days
From permit issuance to completion
City-wide median
17 days
South Calgary is 5 days slower

Recent examples in South Calgary

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13209Improvement2026-07-152026-08-0723$15
BP2026-11400Improvement2026-06-212026-07-0716$5K
BP2026-04208ImprovementWest Era Homes2026-03-192026-06-1992$79K
BP2026-02090Improvement2026-02-112026-04-0250$30K
BP2026-03663Improvement2026-03-102026-03-199$0