How long does a Single Construction Permit permit take in Silver Springs, Calgary?
Median days · Applied → Issued
65 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
509 days
From permit issuance to completion
City-wide median
18 days
Silver Springs is 47 days slower
Recent examples in Silver Springs
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07970 | New | Rectangle Design | 2026-05-08 | 2026-07-09 | 62 | $369K |
| BP2024-25301 | New | Riverview Custom Homes | 2024-12-05 | 2025-02-26 | 83 | $462K |
| BP2024-17509 | New | Greystone Custom Homes | 2024-08-21 | 2024-10-25 | 65 | $329K |