How long does a Commercial / Multi Family Project permit take in Silver Springs, Calgary?

Rolling 24 months · Sample: 13
Median days · Applied → Issued
49 days
Sample: 13 permits, last 24 months
Median days · Issued → Completed
151 days
From permit issuance to completion
City-wide median
42 days
Silver Springs is 7 days slower

Recent examples in Silver Springs

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11667ImprovementJax Builders2026-06-242026-08-2158$2.5M
BP2026-05394Improvement2026-04-072026-06-0559$102K
BP2026-07464Unspecified2026-05-042026-05-062$2K
BP2026-02649Improvement2026-02-232026-05-0470$39K
BP2025-23602Improvement2025-12-112026-03-25104$4.5M