How long does a Residential Improvement Project permit take in Silver Springs, Calgary?

Rolling 24 months · Sample: 113
Median days · Applied → Issued
22 days
Sample: 113 permits, last 24 months
Median days · Issued → Completed
80 days
From permit issuance to completion
City-wide median
17 days
Silver Springs is 5 days slower

Recent examples in Silver Springs

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14620Improvement2026-08-042026-09-0936$100K
BP2026-09193ImprovementLux Windows and Glass2026-05-252026-08-2693$8K
BP2026-14769ImprovementGreenfox Windows and Doors2026-08-052026-08-2621$2K
BP2026-15494Improvement2026-08-142026-08-2612$5K
BP2026-13931Improvement2026-07-242026-08-1219$2K