How long does a Single Construction Permit permit take in Richmond, Calgary?

Rolling 24 months · Sample: 60
Median days · Applied → Issued
36 days
Sample: 60 permits, last 24 months
Median days · Issued → Completed
355 days
From permit issuance to completion
City-wide median
18 days
Richmond is 18 days slower

Recent examples in Richmond

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08307NewHbc Custom Homes2026-05-132026-08-28107$346K
BP2026-13106NewNew Realm Homes2026-07-142026-08-2845$269K
BP2026-13108NewNew Realm Homes2026-07-142026-08-2845$269K
BP2026-08305NewHbc Custom Homes2026-05-132026-07-3078$346K
BP2026-11630NewSilverpoint Homes2026-06-242026-07-2834$524K