How long does a Residential Improvement Project permit take in Richmond, Calgary?

Rolling 24 months · Sample: 102
Median days · Applied → Issued
29 days
Sample: 102 permits, last 24 months
Median days · Issued → Completed
172 days
From permit issuance to completion
City-wide median
17 days
Richmond is 12 days slower

Recent examples in Richmond

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14886Improvement2026-08-062026-09-0934$4K
BP2026-14279ImprovementElevate Design Projects2026-07-292026-09-0235$77K
BP2026-08308NewHbc Custom Homes2026-05-132026-08-28107$39K
BP2026-13107NewNew Realm Homes2026-07-142026-08-2845$77K
BP2026-13109NewNew Realm Homes2026-07-142026-08-2845$77K