How long does a Commercial / Multi Family Project permit take in Richmond, Calgary?

Rolling 24 months · Sample: 23
Median days · Applied → Issued
77 days
Sample: 23 permits, last 24 months
Median days · Issued → Completed
102 days
From permit issuance to completion
City-wide median
42 days
Richmond is 35 days slower

Recent examples in Richmond

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13646ImprovementImpact Construction2026-07-212026-08-2636$980K
BP2026-02343NewDream Ridge Homes2026-02-172026-08-25189$517K
BP2026-13647ImprovementImpact Construction2026-07-212026-08-1727$980K
BP2026-02692NewRg Townhomes2026-02-232026-08-16174$1.1M
BP2026-11698ImprovementButtcon West2026-06-252026-07-1419$670K