How long does a Single Construction Permit permit take in Ramsay, Calgary?

Rolling 24 months · Sample: 19
Median days · Applied → Issued
63 days
Sample: 19 permits, last 24 months
Median days · Issued → Completed
229 days
From permit issuance to completion
City-wide median
18 days
Ramsay is 45 days slower

Recent examples in Ramsay

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12659NewZenith Construction2026-07-082026-09-1165$490K
BP2026-12657NewZenith Construction2026-07-082026-08-1740$490K
BP2026-12263NewVbuild Homes2026-07-022026-07-3028$283K
BP2026-12265NewVbuild Homes2026-07-022026-07-3028$283K
BP2026-11938NewDapper Built2026-06-272026-07-2124$226K