How long does a Single Construction Permit permit take in Ramsay, Calgary?
Median days · Applied → Issued
63 days
Sample: 19 permits, last 24 months
Median days · Issued → Completed
229 days
From permit issuance to completion
City-wide median
18 days
Ramsay is 45 days slower
Recent examples in Ramsay
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12659 | New | Zenith Construction | 2026-07-08 | 2026-09-11 | 65 | $490K |
| BP2026-12657 | New | Zenith Construction | 2026-07-08 | 2026-08-17 | 40 | $490K |
| BP2026-12263 | New | Vbuild Homes | 2026-07-02 | 2026-07-30 | 28 | $283K |
| BP2026-12265 | New | Vbuild Homes | 2026-07-02 | 2026-07-30 | 28 | $283K |
| BP2026-11938 | New | Dapper Built | 2026-06-27 | 2026-07-21 | 24 | $226K |