How long does a Commercial / Multi Family Project permit take in Ramsay, Calgary?

Rolling 24 months · Sample: 17
Median days · Applied → Issued
55 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
125 days
From permit issuance to completion
City-wide median
42 days
Ramsay is 13 days slower

Recent examples in Ramsay

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07474NewKalamoir Construction2026-05-042026-08-0593$1.6M
BP2026-07481NewKalamoir Construction2026-05-042026-08-0593$2M
BP2026-07487NewKalamoir Construction2026-05-042026-08-0593$1.2M
BP2026-07493NewKalamoir Construction2026-05-042026-08-0593$1.4M
BP2026-04343Improvement2026-03-202026-07-08110$15K