How long does a Residential Improvement Project permit take in Ramsay, Calgary?
Median days · Applied → Issued
27 days
Sample: 41 permits, last 24 months
Median days · Issued → Completed
199 days
From permit issuance to completion
City-wide median
17 days
Ramsay is 10 days slower
Recent examples in Ramsay
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12660 | New | Zenith Construction | 2026-07-08 | 2026-09-11 | 65 | $41K |
| BP2026-14922 | Improvement | — | 2026-08-07 | 2026-08-23 | 16 | $15K |
| BP2026-12658 | New | Zenith Construction | 2026-07-08 | 2026-08-17 | 40 | $41K |
| BP2026-13616 | Improvement | — | 2026-07-21 | 2026-08-14 | 24 | $0 |
| BP2026-12264 | New | Vbuild Homes | 2026-07-02 | 2026-07-30 | 28 | $58K |