How long does a Residential Improvement Project permit take in Panorama Hills, Calgary?
Median days · Applied → Issued
21 days
Sample: 258 permits, last 24 months
Median days · Issued → Completed
71 days
From permit issuance to completion
City-wide median
17 days
Panorama Hills is 4 days slower
Recent examples in Panorama Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11407 | New | Contractor | 2026-06-22 | 2026-09-08 | 78 | $65K |
| BP2026-16019 | New | — | 2026-08-24 | 2026-09-05 | 12 | $50K |
| BP2026-13941 | Improvement | — | 2026-07-24 | 2026-09-03 | 41 | $15K |
| BP2026-10291 | Improvement | — | 2026-06-06 | 2026-09-02 | 88 | $7K |
| BP2026-14780 | Improvement | Suncoast Enclosures | 2026-08-05 | 2026-08-28 | 23 | $30K |