How long does a Commercial / Multi Family Project permit take in Panorama Hills, Calgary?

Rolling 24 months · Sample: 15
Median days · Applied → Issued
26 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
149 days
From permit issuance to completion
City-wide median
42 days
Panorama Hills is 16 days faster

Recent examples in Panorama Hills

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-04361ImprovementSavvy Fire Protection Savvy Enterprise2026-03-212026-05-0545$24K
BP2025-23529New360 Custom Homes2025-12-102026-01-2243$1.8M
BP2026-00696UnspecifiedBanff Fire and Safety2026-01-162026-01-204$33K
BP2025-23989ImprovementHeritage Property Maintenance2025-12-192026-01-1224$117
BP2025-09694Improvement2025-05-232025-06-1826$1M