How long does a Commercial / Multi Family Project permit take in Panorama Hills, Calgary?
Median days · Applied → Issued
26 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
149 days
From permit issuance to completion
City-wide median
42 days
Panorama Hills is 16 days faster
Recent examples in Panorama Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-04361 | Improvement | Savvy Fire Protection Savvy Enterprise | 2026-03-21 | 2026-05-05 | 45 | $24K |
| BP2025-23529 | New | 360 Custom Homes | 2025-12-10 | 2026-01-22 | 43 | $1.8M |
| BP2026-00696 | Unspecified | Banff Fire and Safety | 2026-01-16 | 2026-01-20 | 4 | $33K |
| BP2025-23989 | Improvement | Heritage Property Maintenance | 2025-12-19 | 2026-01-12 | 24 | $117 |
| BP2025-09694 | Improvement | — | 2025-05-23 | 2025-06-18 | 26 | $1M |