How long does a Demolition permit take in Panorama Hills, Calgary?
Median days · Applied → Issued
15 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
89 days
From permit issuance to completion
City-wide median
4 days
Panorama Hills is 11 days slower
Recent examples in Panorama Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-02723 | Demolition | Bachly Construction | 2026-02-24 | 2026-03-11 | 15 | $0 |
| BP2026-00876 | Demolition | Bachly Construction | 2026-01-20 | 2026-01-28 | 8 | $0 |
| BP2024-25817 | Demolition | Gill S Express | 2024-12-13 | 2024-12-28 | 15 | $0 |